CISA Certified Information Systems Auditor – Question0252

While reviewing the project plan for a new system prior to go-live, an IS auditor notes that the project team has not documented a fallback plan. Which of the following would be the BEST go-live approach in this situation?

A.
Parallel processing
B. Immediate cutover
C. Real-time replication
D. Load balancing

Correct Answer: A