CISA Certified Information Systems Auditor – Question0723

The MOST significant reason for using key performance indicators (KPIs) to track the progress of IT projects against initial targets is that they:

A.
influence management decisions to outsource IT projects
B. identify which projects may require additional funding
C. provide timely indication of when corrective actions need to be taken
D. identify instances where increased stakeholder engagement is required

Correct Answer: D