CISA Certified Information Systems Auditor – Question0856

The PRIMARY reason for allocating sufficient time between the “go-live” phase of a new system and conducting a post-implementation review is to:

A.
update project requirements and design documentation
B. increase availability of system implementation team resources
C. allow the system to stabilize in production
D. obtain sign-off on the scope of post-implementation review

Correct Answer: C