Which of the following would BEST determine whether a post implementation review (PIR) performed by the project management office (PMO) was effective?
A. The review was performed by an external provider.
B. Management approved the PIR report.
C. Lessons learned were implemented.
D. Project outcomes have been realized.
A. The review was performed by an external provider.
B. Management approved the PIR report.
C. Lessons learned were implemented.
D. Project outcomes have been realized.