An offsite information processing facility with electrical wiring, air conditioning and flooring, but no computer or communications equipment, is a: A. cold site. B. warm site. C. dial-up site. D. duplicate processing facility.
Correct Answer: A
Explanation:
Explanation:
A cold site is ready to receive equipment but does not offer any components at the site in advance of the need. A warm site is an offsite backup facility that is partially configured with network connections and selected peripheral equipment-such as disk and tape units, controllers and CPUs-to operate an information processing facility. A duplicate information processing facility is a dedicated, self-developed recovery site that can back up critical applications.