CISA Certified Information Systems Auditor – Question1718

Which of the following tasks should be performed FIRST when preparing a disaster recovery plan?

A.
Develop a recovery strategy.
B. Perform a business impact analysis.
C. Map software systems, hardware and network components.
D. Appoint recovery teams with defined personnel, roles and hierarchy.

Correct Answer: B

Explanation:

Explanation:
The first step in any disaster recovery plan is to perform a business impact analysis. All other tasks come afterwards.