CISA Certified Information Systems Auditor – Question1763

During the design of a business continuity plan, the business impact analysis (BIA) identifies critical processes and supporting applications. This will PRIMARILY influence the:

A.
responsibility for maintaining the business continuity plan.
B. criteria for selecting a recovery site provider.
C. recovery strategy.
D. responsibilities of key personnel.

Correct Answer: C

Explanation:

Explanation:
The most appropriate strategy is selected based on the relative risk level and criticality identified in the business impact analysis (BIA.) The other choices are made after the selection or design of the appropriate recovery strategy.