CISA Certified Information Systems Auditor – Question2008

In a large organization, IT deadlines on important projects have been missed because IT resources are not prioritized properly. Which of the following is the BEST recommendation to address this problem?

A.
Implement project portfolio management.
B. Implement an integrated resource management system.
C. Implement a comprehensive project scorecard.
D. Revisit the IT strategic plan.

Correct Answer: A