Who is ultimately responsible for providing requirement specifications to the software- development team?

A.
The project sponsor
B. The project members
C. The project leader
D. The project steering committee

Correct Answer: A

Explanation:

Explanation:
The project sponsor is ultimately responsible for providing requirement specifications to the software-development team.