CISA Certified Information Systems Auditor – Question2490

When should plans for testing for user acceptance be prepared?

A.
In the requirements definition phase of the systems-development project
B. In the feasibility phase of the systems-development project
C. In the design phase of the systems-development project
D. In the development phase of the systems-development project

Correct Answer: A

Explanation:

Explanation:
Plans for testing for user acceptance are usually prepared in the requirements definition phase of the systems-development project.