Based on the guidance of internal audit, an IT steering committee is considering the use of a balanced scorecard to evaluate its project management process. Which of the following is the GREATEST advantage to using this approach?

A.
Project schedule and budget management will improve.
B. Performance is measured from different perspectives.
C. Information is provided in a consistent and timely manner.
D. Project will be prioritized based on value.

Correct Answer: B