CISA Certified Information Systems Auditor – Question2720

In reviewing the IS short-range (tactical) plan, an IS auditor should determine whether:

A.
there is an integration of IS and business staffs within projects.
B. there is a clear definition of the IS mission and vision.
C. a strategic information technology planning methodology is in place.
D. the plan correlates business objectives to IS goals and objectives.

Correct Answer: A

Explanation:

Explanation:
The integration of IS and business staff in projects is an operational issue and should be considered while reviewing the short-range plan. A strategic plan would provide a framework for the IS short-range plan. Choices B, C and D are areas covered by a strategic plan.