An IS auditor has been asked to participate in project initiation meetings for a critical project. The IS auditor's MAIN concern should be that the:
A. complexity and risks associated with the project have been analyzed.
B. resources needed throughout the project have been determined.
C. project deliverables have been identified.
D. a contract for external parties involved in the project has been completed.
A. complexity and risks associated with the project have been analyzed.
B. resources needed throughout the project have been determined.
C. project deliverables have been identified.
D. a contract for external parties involved in the project has been completed.