The phases and deliverables of a system development life cycle (SDLC) project should be determined:
A. during the initial planning stages of the project.
B. after early planning has been completed, but before work has begun.
C. throughout the work stages, based on risks and exposures.
D. only after all risks and exposures have been identified and the IS auditor has recommended appropriate controls.
A. during the initial planning stages of the project.
B. after early planning has been completed, but before work has begun.
C. throughout the work stages, based on risks and exposures.
D. only after all risks and exposures have been identified and the IS auditor has recommended appropriate controls.