During the development of an application, the quality assurance testing and user acceptance testing were combined. The MAJOR concern for an IS auditor reviewing the project is that there will be:
A. increased maintenance.
B. improper documentation of testing.
C. inadequate functional testing.
D. delays in problem resolution.