Normally, it would be essential to involve which of the following stakeholders in the initiation stage of a project? A. System owners B. System users C. System designers D. System builders
Correct Answer: A
Explanation:
Explanation:
System owners are the information systems (project) sponsors or chief advocates. They normally are responsible for initiating and funding projects to develop, operate and maintain information systems. System users are the individuals who use or are affected by the information system.
Their requirements are crucial in the testing stage of a project. System designers translate business requirements and constraints into technical solutions. System builders construct the system based on the specifications from the systems designers. In most cases, the designers and builders are one and the same.