When performing an audit of a client relationship management (CRM) system migration project, which of the following should be of GREATEST concern to an IS auditor?
A. The technical migration is planned for a Friday preceding a long weekend, and the time window is too short for completing all tasks.
B. Employees pilot-testing the system are concerned that the data representation in the new system is completely different from the old system.
C. A single implementation is planned, immediately decommissioning the legacy system.
D. Five weeks prior to the target date, there are still numerous defects in the printing functionality of the new system’s software.
A. The technical migration is planned for a Friday preceding a long weekend, and the time window is too short for completing all tasks.
B. Employees pilot-testing the system are concerned that the data representation in the new system is completely different from the old system.
C. A single implementation is planned, immediately decommissioning the legacy system.
D. Five weeks prior to the target date, there are still numerous defects in the printing functionality of the new system’s software.