When reviewing a hardware maintenance program, an IS auditor should assess whether:
A. the schedule of all unplanned maintenance is maintained.
B. it is in line with historical trends.
C. it has been approved by the IS steering committee.
D. the program is validated against vendor specifications.
A. the schedule of all unplanned maintenance is maintained.
B. it is in line with historical trends.
C. it has been approved by the IS steering committee.
D. the program is validated against vendor specifications.