Time constraints and expanded needs have been found by an IS auditor to be the root causes for recent violations of corporate data definition standards in a new business intelligence project.
Which of the following is the MOST appropriate suggestion for an auditor to make?
A. Achieve standards alignment through an increase of resources devoted to the project
B. Align the data definition standards after completion of the project
C. Delay the project until compliance with standards can be achieved
D. Enforce standard compliance by adopting punitive measures against violators