CISM Certified Information Security Manager – Question0221
Which of the following risks would BEST be assessed using quantitative risk assessment techniques? A. Customer data stolen B. An electrical power outage C. A web site defaced by hackers D. Loss of the software development team
Correct Answer: B
Explanation:
Explanation:
The effect of the theft of customer data or web site defacement by hackers could lead to a permanent decline in customer confidence, which does not lend itself to measurement by quantitative techniques. Loss of a majority of the software development team could have similar unpredictable repercussions. However, the loss of electrical power for a short duration is more easily measurable and can be quantified into monetary amounts that can be assessed with quantitative techniques.