CISM Certified Information Security Manager – Question0632
Which of the following tools is MOST appropriate for determining how long a security project will take to implement? A. Gantt chart B. Waterfall chart C. Critical path D. Rapid Application Development (RAD)
Correct Answer: C
Explanation:
Explanation:
The critical path method is most effective for determining how long a project will take. A waterfall chart is used to understand the flow of one process into another. A Gantt chart facilitates the proper estimation and allocation of resources. The Rapid Application Development (RAD) method is used as an aid to facilitate and expedite systems development.