CISM Certified Information Security Manager – Question0938

Which of the following change management activities would be a clear indicator that normal operational procedures require examination? A high percentage of:

A.
similar change requests.
B. change request postponements.
C. canceled change requests.
D. emergency change requests.

Correct Answer: D

Explanation:

Explanation:
A high percentage of emergency change requests could be caused by changes that are being introduced at the last minute to bypass normal chance management procedures. Similar requests, postponements and canceled requests all are indicative of a properly functioning change management process.