CISM Certified Information Security Manager – Question0988

A risk analysis for a new system is being performed. For which of the following is business knowledge MORE important than IT knowledge?

A.
Vulnerability analysis
B. Balanced scorecard
C. Cost-benefit analysis
D. Impact analysis

Correct Answer: B