CISM Certified Information Security Manager – Question0972

Which of the following is MOST critical for prioritizing actions in a business continuity plan (BCP)?

A.
Business impact analysis (BIA)
B. Risk assessment
C. Asset classification
D. Business process mapping

Correct Answer: A