Which of the following is MOST closely associated with a business continuity program?

A.
Confirming that detailed technical recovery plans exist
B. Periodically testing network redundancy
C. Updating the hot site equipment configuration every quarter
D. Developing recovery time objectives (RTOs) for critical functions

Correct Answer: D

Explanation:

Explanation: Technical recovery plans, network redundancy and equipment needs are all associated with infrastructure disaster recovery. Only recovery time objectives (RTOs) directly relate to business continuity.