CISM Certified Information Security Manager – Question1406

Which of the following would be a MAJOR consideration for an organization defining its business continuity plan (BCP) or disaster recovery program (DRP)?

A.
Setting up a backup site
B. Maintaining redundant systems
C. Aligning with recovery time objectives (RTOs)
D. Data backup frequency

Correct Answer: C

Explanation:

Explanation:
BCP, DRP should align with business RTOs. The RTO represents the amount of time allowed for the recovery of a business function or resource after a disaster occurs. The RTO must be taken into consideration when prioritizing systems for recovery efforts to ensure that those systems that the business requires first are the ones that are recovered first.