CISM Certified Information Security Manager – Question0632

Which of the following tools is MOST appropriate for determining how long a security project will take to implement?

A.
Gantt chart
B. Waterfall chart
C. Critical path
D. Rapid Application Development (RAD)

Correct Answer: C

Explanation:

Explanation:
The critical path method is most effective for determining how long a project will take. A waterfall chart is used to understand the flow of one process into another. A Gantt chart facilitates the proper estimation and allocation of resources. The Rapid Application Development (RAD) method is used as an aid to facilitate and expedite systems development.