COBIT 5 Foundation – Question084

What Change Enablement component in the Implementation Life Cycle supports the defining of the target state?

A.
Operating and using the new approaches
B. Forming the implementation team
C. Identifying the role players
D. Communicating outcome

Correct Answer: B