Your project team has completed the quantitative risk analysis for your project work. Based on their findings, they need to update the risk register with several pieces of information. Which one of the following components is likely to be updated in the risk register based on their analysis?
A. Listing of risk responses
B. Risk ranking matrix
C. Listing of prioritized risks
D. Qualitative analysis outcomes