CRISC Certified in Risk and Information Systems Control – Question106

Which of the following is the FOREMOST root cause of project risk? Each correct answer represents a complete solution. Choose two.

A.
New system is not meeting the user business needs
B. Delay in arrival of resources
C. Lack of discipline in managing the software development process
D. Selection of unsuitable project methodology

Correct Answer: CD

Explanation:

Explanation:
The foremost root cause of project risk is:

  • A lack of discipline in managing the software development process
  • Selection of a project methodology that is unsuitable to the system being developed

Incorrect Answers:
A: The risk associated with new system is not meeting the user business needs is business risks, not project risk.
B: This is not direct reason of project risk.