CRISC Certified in Risk and Information Systems Control – Question135

Which of the following is an acceptable method for handling positive project risk?

A.
Exploit
B. Avoid
C. Mitigate
D. Transfer

Correct Answer: A

Explanation:

Explanation: Exploit is a method for handling positive project risk.
Incorrect Answers:
B, C, D: These are all responses which is used for negative risks, and not the positive risk.