You are the project manager of GHT project. You have implemented an automated tool to analyze and report on access control logs based on severity. This tool generates excessively large amounts of results. You perform a risk assessment and decide to configure the monitoring tool to report only when the alerts are marked "critical". What you should do in order to fulfill that?
A. Apply risk response
B. Optimize Key Risk Indicator
C. Update risk register
D. Perform quantitative risk analysis