CRISC Certified in Risk and Information Systems Control – Question170

You are working as a project manager in Bluewell Inc.. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

A.
Qualitative risk analysis
B. Risk audits
C. Quantitative risk analysis
D. Requested changes

Correct Answer: D

Explanation:

Explanation:
Of all the choices given, only requested changes is an output of the monitor and control risks process. You might also have risk register updates, recommended corrective and preventive actions, organizational process assets, and updates to the project management plan.
Incorrect Answers: A, C: These are the plan risk management processes.
B: Risk audit is a risk monitoring and control technique.