CRISC Certified in Risk and Information Systems Control – Question225

You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

A.
Stakeholder management strategy
B. Assessment information of the stakeholders' major requirements, expectations, and potential influence
C. Identification information for each stakeholder
D. Stakeholder classification of their role in the project

Correct Answer: A

Explanation:

Explanation:
The stakeholder management strategy is generally not included in the stakeholder registry because it may contain sensitive information that should not be shared with project team members or certain other individuals that could see the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Incorrect Answers: B, C, D: Stakeholder identification, Assessment information, and Stakeholder classification should be included in the stakeholder register.