Which of the following statements is NOT true regarding the risk management plan?
A. The risk management plan is an output of the Plan Risk Management process.
B. The risk management plan is an input to all the remaining risk-planning processes.
C. The risk management plan includes a description of the risk responses and triggers.
D. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets.
A. The risk management plan is an output of the Plan Risk Management process.
B. The risk management plan is an input to all the remaining risk-planning processes.
C. The risk management plan includes a description of the risk responses and triggers.
D. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets.