You have identified several risks in your project. You have opted for risk mitigation in order to respond to identified risk. Which of the following ensures that risk mitigation method that you have chosen is effective?
A. Reduction in the frequency of a threat
B. Minimization of inherent risk
C. Reduction in the impact of a threat
D. Minimization of residual risk