You are the project manager of GHT project. You have analyzed the risk and applied appropriate controls. In turn, you got residual risk as a result of this. Residual risk can be used to determine which of the following?
A. Status of enterprise's risk
B. Appropriate controls to be applied next
C. The area that requires more control
D. Whether the benefits of such controls outweigh the costs