CRISC Certified in Risk and Information Systems Control – Question294

You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?

A.
Add the risk to the issues log
B. Close the outdated risks
C. Add the risks to the risk register
D. Add the risks to a low-priority watch-list

Correct Answer: B

Explanation:

Explanation: Risks that are now outdated should be closed by the project manager, there is no need to keep record of that.
Incorrect Answers:
A: Risks do not go into the issue log, but the risk register.
C: Identified risks are already in the risk register.
D: Risks with low probability and low impact go on the risk watchlist.