CRISC Certified in Risk and Information Systems Control – Question295

What activity should be done for effective post-implementation reviews during the project?

A.
Establish the business measurements up front
B. Allow a sufficient number of business cycles to be executed in the new system
C. Identify the information collected during each stage of the project
D. Identify the information to be reviewed

Correct Answer: A

Explanation:

Explanation: For effective post-implementation review the business measurements up front is established during the project.
Incorrect Answers:
B: Executing sufficient number of business cycles in the new system is done after the completion of the project. C, D: Identifying the information to be reviewed and information collected during each stage of project is done in pre-project phase and not during project for effective post-implementation review.