Henry is the project sponsor of the JQ Project and Nancy is the project manager. Henry has asked Nancy to start the risk identification process for the project, but Nancy insists that the project team be involved in the process. Why should the project team be involved in the risk identification?
A. So that the project team can develop a sense of ownership for the risks and associated risk responsibilities.
B. So that the project manager can identify the risk owners for the risks within the project and the needed risk responses.
C. So that the project manager isn't the only person identifying the risk events within the project.
D. So that the project team and the project manager can work together to assign risk ownership.
A. So that the project team can develop a sense of ownership for the risks and associated risk responsibilities.
B. So that the project manager can identify the risk owners for the risks within the project and the needed risk responses.
C. So that the project manager isn't the only person identifying the risk events within the project.
D. So that the project team and the project manager can work together to assign risk ownership.