CRISC Certified in Risk and Information Systems Control – Question030

For which of the following risk management capability maturity levels do the statement given below is true? "Real-time monitoring of risk events and control exceptions exists, as does automation of policy management"

A.
Level 3
B. Level 0
C. Level 5
D. Level 2

Correct Answer: C

Explanation:

Explanation: An enterprise’s risk management capability maturity level is 5 when real-time monitoring of risk events and control exceptions exists, as does automation of policy management.
Incorrect Answers:
A, D: In these levels real-time monitoring of risk events is not done.
B: In level 0 of risk management capability maturity model, enterprise does not recognize the importance of considering the risk management or the business impact from IT risk.