Which of the following parameters would affect the prioritization of the risk responses and development of the risk response plan? Each correct answer represents a complete solution. Choose three.
A. Importance of the risk
B. Time required to mitigate risk.
C. Effectiveness of the response
D. Cost of the response to reduce risk within tolerance levels
A. Importance of the risk
B. Time required to mitigate risk.
C. Effectiveness of the response
D. Cost of the response to reduce risk within tolerance levels