CRISC Certified in Risk and Information Systems Control – Question389
Which of the following serve as the authorization for a project to begin? A. Approval of project management plan B. Approval of a risk response document C. Approval of risk management document D. Approval of a project request document
Correct Answer: D
Explanation:
Explanation: Approval of a project initiation document (PID) or a project request document (PRD) is the authorization for a project to begin.
Incorrect Answers:
A: Project management plan is being made after the project is being authorized.
B: Risk response document comes under risk management process, hence the latter phase in project development process.
C: Risk management document is being prepared later after the project initiation, during the risk management plan. It has no scope during project initialization.