CRISC Certified in Risk and Information Systems Control – Question463

Which of the following is the BEST metric to demonstrate the effectiveness of an organization’s change management process?

A.
Average time to complete changes
B. Increase in the number of emergency changes
C. Percent of unauthorized changes
D. Increase in the frequency of changes

Correct Answer: A