CRISC Certified in Risk and Information Systems Control – Question081

What are the requirements of monitoring risk? Each correct answer represents a part of the solution. Choose three.

A.
Information of various stakeholders
B. Preparation of detailed monitoring plan
C. Identifying the risk to be monitored
D. Defining the project's scope

Correct Answer: BCD

Explanation:

Explanation:
It is important to first understand the risk to be monitored, prepare a detailed plan and define the project’s scope for monitoring risk. In the case of a monitoring project, this step should involve process owners, data owners, system custodians and other process stakeholders.
Incorrect Answers:
A: Data regarding stakeholders of the project is not required in any phase of risk monitoring.