CRISC Certified in Risk and Information Systems Control – Question023
What is the process for selecting and implementing measures to impact risk called? A. Risk Treatment B. Control C. Risk Assessment D. Risk Management
Correct Answer: A
Explanation:
Explanation: The process for selecting and implementing measures for impacting risk in the environment is called risk treatment.
Incorrect Answers:
C: The process of analyzing and evaluating risk is called risk assessment.
D: Risk management is the coordinated activities for directing and controlling the treatment of risk in the organization.