CRISC Certified in Risk and Information Systems Control – Question045

Where are all risks and risk responses documented as the project progresses?

A.
Risk management plan
B. Project management plan
C. Risk response plan
D. Risk register

Correct Answer: D

Explanation:

Explanation: All risks, their responses, and other characteristics are documented in the risk register. As the project progresses and the conditions of the risk events change, the risk register should be updated to reflect the risk conditions.
Incorrect Answers:
A: The risk management plan addresses the project management’s approach to risk management, risk identification, analysis, response, and control.
B: The project management plan is the overarching plan for the project, not the specifics of the risk responses and risk identification.
C: The risk response plan only addresses the planned risk responses for the identified risk events in the risk register.