What are the requirements of monitoring risk? Each correct answer represents a part of the solution. Choose three.
A. Information of various stakeholders
B. Preparation of detailed monitoring plan
C. Identifying the risk to be monitored
D. Defining the project's scope
A. Information of various stakeholders
B. Preparation of detailed monitoring plan
C. Identifying the risk to be monitored
D. Defining the project's scope