CRISC Certified in Risk and Information Systems Control – Question092

You are the project manager of a large networking project. During the execution phase the customer requests for a change in the existing project plan. What will be your immediate action?

A.
Update the risk register.
B. Ask for a formal change request.
C. Ignore the request as the project is in the execution phase.
D. Refuse the change request.

Correct Answer: B

Explanation:

Explanation:
Whenever the customer or key stakeholder asks for a change in the existing plan, you should ask him/her to submit a formal change request. Change requests may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality.
Incorrect Answers: A, C, D: The first action required is to create a formal change request, if a change is requested in the project.