CRISC Certified in Risk and Information Systems Control – Question117

Jeff works as a Project Manager for www.company.com Inc. He and his team members are involved in the identify risk process. Which of the following tools & techniques will Jeff use in the identify risk process? Each correct answer represents a complete solution. (Choose three.)

A.
Information gathering technique
B. Documentation reviews
C. Checklist analysis
D. Risk categorization

Correct Answer: ABC

Explanation:

Explanation:
The various tools & techniques used in the identify risk process are as follows:

  • Documentation reviews
  • Information gathering technique
  • Checklist analysis
  • Assumption analysis
  • Diagramming techniques
  • SWOT analysis
  • Expert judgment